Water and wastewater master plan
Summary
New sewer tap fees now better match actual material and labor costs — developers and builders hooking into the system will pay more.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jun 2, 2026.
Impact analysis
Higher tap fees for anyone making a new sewer connection.
Existing utility ratepayers, since growth pays more of its own way.
Developers and property owners making new sewer connections.
Mentions & discussions (3)
Board of Aldermen - Jun 2, 2026
Waggoner Engineering will develop the city's water, sewer and stormwater master plan — a prerequisite for federal grant funding on future utility projects.
Board of Aldermen - May 19, 2026
The board authorized bidding for new water wells at mTrade Park, a 20-inch water main along Pat Patterson Parkway, a sewer extension to Sandy Cove, and a federal grant-funded flood monitoring system on local creeks.
Board of Aldermen - Jan 6, 2026
New sewer tap fees now better match actual material and labor costs — developers and builders hooking into the system will pay more.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Oxford
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.