Historic City Hall renovation nearing completion
Summary
The board approved fixing City Hall's stairs, stairwell lighting, and basement (untouched since 1973), authorized the Development Services Annex renovation contract, and moved forward on the long-delayed Activity Center roof.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed May 5, 2026.
Impact analysis
The storm drain and City Hall change orders add costs; the roundabout change order reduced its cost by about $10,000.
City employees and residents using City Hall, the Annex, and the Activity Center.
Mentions & discussions (3)
Board of Aldermen - May 5, 2026
The board approved fixing City Hall's stairs, stairwell lighting, and basement (untouched since 1973), authorized the Development Services Annex renovation contract, and moved forward on the long-delayed Activity Center roof.
Board of Aldermen - Jan 20, 2026
The fifth — and likely final — change order for the historic City Hall renovation was approved. Expect the building fully done by March 5.
Board of Aldermen - Jan 6, 2026
City Hall leaks every hard rain. The board approved $60,246 in copper roof repairs with a 20-year warranty, spending about $18,000 more than the 10-year option for the longer coverage.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Oxford
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.